The Water Action Plan Committee (WAPC) meeting began at 9:30 a.m. in Golden, Colorado. All members of the WAPC members were present. The minutes of the August 17, 1999, WAPC meeting were approved as amended. The distribution of information via Electronic Mail (E-Mail) to the WAPC was discussed. E-Mail will be used to transmit information to the WAPC, as needed.
Curt Brown, EIS (Environmental Impact Statement) Manger, briefed the WAPC on the approach the EIS Team anticipates using in the analysis of yield for water alternatives. The EIS Manager's briefing covered the following topics.
Models:
Models to be used include: North Platte Model, Central Platte OPSTUDY Model, and South Platte ExcelCRAM Model.
Time Period:
Accounting:
Baseline:
Yield/Score:
Pulse Flows:
Other Elements:
Conservation:
After a break from 11 a.m. to 11:15 a.m., the meeting continued with a discussion of the schedule for the Peer Review of the Boyle Report, Boyle Report, and Water Action Plan. Nebraska representatives brought forward a request by Nebraska water users to extend the comment period for the draft Boyle Report to November 1. In addition, changes in the existing schedule were suggested for the final Boyle Report, draft Water Action Plan, and final Water Action Plan. The following concerns regarding the schedule were expressed and discussed.
After a lunch break from 12:30 p.m. to 1:50 p.m., the meeting continued with further discussion of the schedule. After considerable discussion, the following schedule was adopted. However, reservations regarding the revised schedule still exist. A table with the revised dates are shown below.
|
|
|
|
|
WMC Reconnaissance Study |
||
|
September 3, 1999 |
November 1, 1999 |
|
September 24, 1999 |
September 24, 1999 |
|
October 15, 1999 |
December 13, 1999 |
|
Water Action Plan |
||
|
December 13, 1999 |
December 13, 1999 |
|
January 10, 2000 |
Feb-May 15, 2000 |
Heather Thompson of Boyle Engineering reviewed with the WAPC the results of the options/scenarios prepared by Boyle. The eight (8) scenarios of combining alternatives as directed by WAPC included:
1. Least cost to provide 60,000 to 80,000 ac-ft/yr of reductions
2. Equal cost per state to provide 60,000 to 80,000 ac-ft/yr of reductions
3. Equal reductions provided by each State
4. Fair share water allocation (40%-NE, 40%-CO, 20%-WY) to provide 130,000 to 150,000 ac-ft/yr of reduction assuming Path Mod (23,000 ac-ft/yr); Tamarack (10,000 ac-ft/yr); and McConaughy EA (37,000 ac-ft/yr)
5. Fair share water allocation (40%-NE, 40%-CO, 20%-WY) to provide 130,000 to 150,000 ac-ft/yr of reduction assuming Path Mod (17,500 ac-ft/yr); Tamarack (7,500 ac-ft/yr); and McConaughy EA (45,500 ac-ft/yr) based on 90 kaf yields
6. Fair share water allocation (40%-NE, 40%-CO, 20%-WY) to provide 60,000 to 80,000 ac-ft/yr of reductions
7. Fair share cost allocation (40%-NE, 40%-CO, 20%-WY) to provide 130,000 to 150,000 ac-ft/yr of reduction assuming the costs are credited to the three states for the Path Mod, Tamarack, and McConaughy EA:
- Pathfinder Mod - WY -- $3.5 Million
- Tamarack - CO -- $ 1.2 Million
- McConaughy - NE -- $9.0 Million
8. Fair share cost allocation (40%-NE, 40%-CO, 20%-WY) to provide 60,000 to 80,000 ac-ft/yr of reductions
The WAPC discussed potential scenarios that could be used to begin the process of formulation of the Water Action Plan. The discussion focused on the concepts of economics (least cost) and a fair share of water from each state. It was suggested that two scenarios be created: one with a fair share of water approach and the other with a least cost approach. Considerable debate on whether both of these scenarios should be looked at ensued and no agreement was reached by the WAPC. Nebraska representatives indicated they would prepare their own scenario regarding fair share of water and present it at the October meeting for discussion. It is also anticipated other WAPC members will prepare scenarios to be discussed at the October meeting. Any such scenarios created are done solely by WAPC members of their own choice and do not constitute support by all WAPC members, nor direction from the WAPC. It is anticipated these scenarios will provide a starting point for discussion at the next meeting.
It was suggested to use EIS resources to run existing EIS models to see how one selected alternative from each state scores in combination with the three existing projects as a comparison to Boyle Report yields. Each member was encouraged to identify one alternative and provide it to the WAPC Chair by September 24, so cumulative analysis with the three projects could be done. Technical questions for this effort are to be coordinated through the WAPC Chair. It is anticipated the results of the EIS Scenarios will be discussed at October meeting.
The next meeting of the WAPC will be October 14, 1999,at the Country Inn& Suites in Kearney, Nebraska. The meeting will start at 8 a.m. and end at 12 p.m. A tour of habitat restoration work/areas will begin at 1 p.m. on October 14, 1999.
Agenda items for the upcoming meeting will include presentation/discussion the scenarios created by Nebraska and others and results of yield evaluations using the EIS models. The WAPC was asked to provide any additional agenda items to the WAPC Chair.
The meeting adjourned at 5:30 p.m