Agenda and Minutes
Paul Tebbel called the meeting to order at 9:20 a.m. and welcomed
the group. Paul noted minor changes to the agenda. Suggested changes
to the
November minutes were
made and the minutes as amended were accep
ted by
consensus.Concern was raised about the circulation
of technical documents by the FWS, including the
whooping crane model report and the final minutes
from the species recovery workshop. It was noted
that these topics were FWS issues and were not
necessarily full Technical Committee (TC) activities
or issues, therefore, the FWS distributed the information
first to the Governance Committee (GC). There was
some discussion regarding the role of the TC in
these issues and other technical matters that may
develop during the Cooperative Agreement (CA) and
Program. Paul Tebbel noted that if technical information
goes before the GC (e.g., State Depletion Plans),
the GC needs to insure the information and any
necessary action is delegated to the proper subcommittee.
This will help keep proper lines of communication
open.
Status Reports
Governance Committee Paul
reported that the major topic discussed during
the last GC meeting was the Cooperative Agreement
Extension.
Black and White Aerial PhotographyClayton
Derby reported that the contract end date
was changed from December 15, 2000 to May
1, 2001. This will allow for a possible early
spring flight before leaf out.
Cottonwood
Ranch Property Monitoring and Research ProjectJim
Jenniges reported that no further work on
the monitoring and research project was done
since the last TC meeting. Jim gave a brief
update of the monitoring and research activities
at Cottonwood Ranch in 2000.
Cooperative
Agreement Extension and Critical Path
Clayton
stated that the GC had formally extended
the CA to June 30, 2003, by unanimous vote
during a December 15 conference call. Clayton
used overheads to review milestones and subtasks
identified in the Extension Document needing
completion by May 2001 (see attachment).
It was noted that several of the milestones
have direct or indirect TC involvement. Clayton
stated that since the GC plans to meet bimonthly,
draft documents due in May need to be presented
to them for discussion at their March meeting.
This will allow the TC time to revise the
documents based on GC input and for the GC
to approve the work and complete the milestones
at the May GC meeting.The TC discussed what
was meant by "monitoring categories" as
identified in the Extension Document. Sharon
Whitmore and others explained that the FWS
needs the draft
Integrated Monitoring
and Research Plan (IMRP) more fleshed
out to help them identify and analyze in
the Biological Opinion how and what the Program
will be monitoring.The TC also discussed
how peer review of individual protocols fits
into the tight schedule for implementation
of completed monitoring protocols in 2001
(e.g., tern and plover, whooping crane) and
how the entire IMRP will be peer reviewed.
It was suggested that the TC conduct just
the informal reviews before field implementation
of the monitoring protocols at a pilot/demonstration
project level. Protocols would then be updated
and modified based on the first year's information
and then sent to independent peer reviewers.
The TC asked Paul to communicate this possible
change in protocols after a field season
or pilot/demonstration project to the GC.
It was noted that once all protocols are
completed and incorporated into the IMRP,
the TC will decide if the entire document
should be peer reviewed. The peer review
would help insure the monitoring and research
package will answer the questions the Program
wants answered. Some time was spent discussing
how the TC can move funding requests through
the Finance Committee and GC in time for
field implementation of protocols at any
level (i.e., pilot project or full implementation)
in 2001.The TC discussed what the objectives
of the whooping crane protocol should be,
and Paul Tebbel noted that the objectives
might change slightly after a pilot project.
Paul briefly updated the TC regarding current
efforts by the National Wildlife Federation
and Nebraska Wildlife Federation to conduct
a ground survey for whooping cranes starting
in 2001 using the TC's protocol. Mike Fritz
also updated the TC regarding NGPC's ongoing
project to compile historic tern, plover,
and whooping crane data. Sharon Whitmore
and Paul Tebbel noted that for scheduling
purposes the TC needs to decide if they want
to implement the whooping crane monitoring
protocol this spring. There was some discussion
regarding who could conduct the actual monitoring:
volunteers; technicians hired by the Trust,
NGPC, or others; current personnel; or hired
contractors. The TC discussed how to get
the whooping crane monitoring funded in time
for implementation in spring 2001. The group
suspended further discussion of the whooping
protocol until the protocol was officially
discussed later in the meeting (see below).
Protocols
General
Monitoring Protocol Mark
Peyton updated the TC on a vegetation monitoring
meeting held on December 20, 2000. Mark reported
that the Districts, NGPC and FWS (members
of the Monitoring Oversight Committee for
the Districts' licenses) had adopted the
Project Land and Management Area sections
of the protocol as amended at the meeting
for implementation in 2001. Mark briefly
went over the design and methods described
for these two scales of monitoring and explained
that there was no discussion regarding the
system level monitoring at the December 20
meeting. Mark explained that the Districts
anticipate funding the monitoring at the
following level of effort: 12 transects at
Cottonwood Ranch and 14 at Jeffrey Island
for the Project Land level and 100 plots
at each property in the Management Areas
(one plot per six acres). The RFP/proposal
process for implementation of the protocol
will help serve as an informal review process
for the final protocol. Paul Tebbel noted
that if the TC desires more work to be completed
than is currently planned, the TC should
request funding from the Finance Committee
and GC.The TC spent some time discussing
the overall objective of the proposed monitoring
and specifically the need of the Monitoring
Oversight Committee to have in place a protocol
to collect baseline vegetation information.
It was noted that information related to
birds, mammal, invertebrates and other fauna
will not be collected through this protocol.
If the TC desires system level monitoring
of the fauna, separate protocols will be
needed. It was noted that the General Monitoring
protocol should tie in, by reference at a
minimum, the GIS protocol and protocols for
aerial photography yet to be written. The
TC spent limited time discussing the geomorphology
aspects of the general monitoring protocol.
In particular the TC wanted clarification
in the protocol on the analysis of data related
to bed load and suspended sediment collected
at gauge locations not systematically placed
throughout the system. It was noted that
more information related to sediment and
the geomorphology will be available in future
given the current efforts by the BOR, USGS,
and states. Comments on the protocol are
due to the Executive Director's office by
January 8, 2001.
Whooping Crane MonitoringPaul
Tebbel started the discussion with again
asking if the TC wanted to implement any
whooping crane monitoring in spring 2001.
There was a discussion regarding the pros
and cons of implementing all or part of the
protocol this spring. The option of starting
implementation of the protocol in fall 2001
was also discussed. Paul noted that it would
be best to fully implement the protocol so
that the short use by whooping cranes in
the spring is not missed. This is in comparison
to only implementing the protocol for one
or two weeks as a pilot project. If monitoring
is only conducted for one or two weeks a
whooping crane stopover might be missed.
There was general agreement to conduct some
whooping crane monitoring effort this spring.
There was another discussion regarding who
could coordinate and conduct the monitoring
activities. It was decided that a small group
of Dave Carlson, Mike Fritz, Paul Tebbel,
Paul Obert, Paul Currier, and Bob Henszey
would work with the Executive Director's
office to determine what might be possible
to implement this spring, cost of implementation,
and who would conduct the work. This group
will also help refine and edit the protocol
in the future before full TC review and discussion.
The small group will meet January 3, 2001,
at 9:00 at the Trust facility near Alda.
A second meeting or conference call was tentatively
planned for January 16 at 1:00 p.m. at either
Grand Island or the Trust. Paul asked for
and received TC concurrence that he can bring
a heads-up on what the TC is planning regarding
whooping cranes to the GC before the entire
TC reviews and discusses the issue further.
Tern
and Plover MonitoringPaul
Tebbel asked if the TC wants to conduct an
independent peer review of the tern and plover
protocol at this time. The TC agreed to conduct
the peer review after completion of a pilot
project, or full implementation of the protocol,
this field season. A small working group
of Jim Jenniges, Erika Wilson, Mark Peyton
and Mike Fritz was identified to help with
further work as needed on the protocol.
PrioritiesClayton
Derby went through the protocols identified
as top priority in the TC's January 11, 2000, "Proposal
for Writing Monitoring Protocols for the
Cooperative Agreement and Proposed Program".
Clayton reported that four of the seven protocols
identified are currently being drafted (i.e.,
tern and plover, whooping crane, and general
monitoring which combines two of the identified
top priorities). Clayton then asked for direction
on what protocols should be worked on next.
The TC identified drafting the protocol for
database construction as highest priority
among the remaining three identified in the
proposal. The TC also gave direction to the
Executive Director's office that the highest
priority overall should be given to writing
Environmental Account related protocols.
Protocols should look at evaluating the objectives
of specific types of flows (e.g., pulse flows,
flows for fish survival). The TC gave specific
direction to the Executive Director's office
to first begin work on protocols to evaluate
flows on seedling removal/channel maintenance
and fish survival. This is a change from
the protocols first identified as highest
priority in January 2000. These two protocols
were selected as they might be implemented
in the summer of 2001 and not because they
were more important than protocols that will
evaluate other types of flows. Paul Tebbel
noted that a monitoring priority for the
GC would likely be to fill baseline data
gaps
Future Meetings
Technical
Committee -
1-5
p.m. MST January 23 and 8 a.m.-12 p.m. MST
January 24,
Ogallala, Nebraska, site TBD.Whooping Crane
Monitoring Subgroup - 9 a.m. CST, January
3, Trust Facility, Alda, NebraskaWhooping
Crane Monitoring Subgroup - tentative meeting
scheduled for January 16, 1-5 p.m., site
TBD.
1. January 31, 2001 -
DOI will deliver to the GC quantitative data,
modeling assumptions, input, etc on the sed/veg
model (C1-EXT)2. March 1, 2001 -
FWS and GC identify components of continued
jeopardy under the existing proposed Program
and other NEPA/ESA alternatives (A3-EXT)POSSIBLE
TC INVOLVEMENT3. March 31, 2001 -
LC and Executive Director's office develop
method to track lands offered to the
Program (L2-EXT)4. March -
TC implement protocols as available
(Whooping Crane protocol) (R1-EXT) TC TASK5. May 1, 2001 -
Agreement on monitoring categories
(what is to be monitored vs. available
funding) (Existing R-milestones; IMRP) TC
TASK6. May 1, 2001 -
Land Policy Statement agreed to
by GC (L3-EXT)7. May 1, 2001 -
GC agree on an allocation of
committee budgets for the CA extension (A1-EXT)
POSSIBLE TC INVOLVEMENT8. May 1, 2001 -
For each state's depletion
plan: identify types of projects covered
and analysis of potential effects
on pulse flows (W1-EXT, W2-EXT,
W4-EXT)9. May 15, 2001 -
Habitat Protection Plan agreed
to by GC (L1-EXT) TC INVOLVEMENT;
NEEDED TC ACTION
2. January 2001 -
complete/update drafts of documents listed above3. January TC Meeting -
Discuss drafts4. Mid-February -
TC written comments on draft documents5. Late February TC Meeting -
Discuss comments and revised drafts6. March 7, 2001 -
Distribute draft documents to GC
for review7. March 22, 2001 -
GC discusses draft documents at
GC meeting8. April 9, 2001 -
Written comments back from GC9. April 16, 2001 -
revised documents back to TC10. Late April (4/25) -
TC Meeting to review GC comments11. May 2, 2001 -
Final written TC comments
on all documents12. May 2-May 11 -
Incorporate final TC
comments13. May 11, 2001 -
Documents to GC for
mid/late May GC meeting where
documents accepted