See other minutes at:
Technical
Committee / Land
Committee / Water
Management Committee / Water
Action Plan Committee
Issues and Decisions
RPA Sufficiency Meeting
May 16, 2001
Denver Water
Denver, Colorado
Issues Raised and Discussed
Sediment
- The FWS is viewing the sediment issue now similar to the way
the water issue was viewed during CA negotiations. The FWS's best
available data suggests that the proposed Program would cause the
channel, and habitat for the target species, to continue to
deteriorate. The FWS recognizes that there is no agreement on the
issue and it should be approached through monitoring and research
projects, with peer review, during the Program.
- The FWS is not suggesting the Program address the problem by
management of the river channel over the entire 90-mile
reach.
- There is no consensus that there is a problem and the states
would like to use the results of the Parsons study to help define
the problem and identify potential solutions, if needed.
- There is general agreement by the parties that this issue can
be resolved, but no agreement was reached on when formal
discussions should occur regarding what specific approach should
be taken or when implementation of the approach would be
appropriate. Information made available through the states'
Parsons study will help identify a timetable and process for
addressing the issue. All parties need to be open to the findings
from the Parsons study.
- There is concern that only two weeks exist after conclusion of
the Parsons study for discussion and decisions on what direction
should be taken during the Program. A suggestion was made to
begin discussion on the issue in parallel with the Parsons study.
Amount and Location of Land Needed by the proposed
Program
- The FWS's main concern is that in-channel habitat loss is
migrating downstream. The Program should find out what can be done
to address this migration and protect and restore 10,000 acres in
habitat complexes. The Program should protect downstream areas
first, but not abandon the pockets of habitat in upstream areas.
Management will be more expensive in the upper areas of the river.
- The FWS still believes that the 29,000 acre long term
objective of the Program, appropriately arrayed as identified in
the Cooperative Agreement, is sufficient for the target species,
but they are concerned with the entire river. If the river
continues to degrade overall, it will make maintenance of Program
lands very difficult. Channel maintenance is a means of
protecting habitat for target species.
Species Habitat
- Concern was raised that there is not an inventory of whooping
crane and tern/plover habitat and that it will be difficult to
determine where the Program should focus. One suggested solution
was to proceed with the Habitat Protection Plan during the first
increment of the Program and allow the species to tell us if there
is enough habitat in the correct configuration through monitoring,
research, and adaptive management.
- Concern was raised that the Program will be measured against a
change in channel width. The FWS stated that the measure for the
Program would be benefit to species and their habitat; channel
width is only one component of species habitat.
- The Program should attempt to provide the best habitat
possible for the species regardless of whether it is classified as
suitable or preferred. FWS clarified that they view these terms
as equivalent.
Land Management
- A cost effective Program must rely on both mechanical and "natural processes" to restore and maintain habitat.
Pulse Flows
- The FWS cannot say what proportion of flows above targets can
be used in the WAP and Depletions Plans. The states will need
this information before the Program begins to insure they are
operating projects correctly.
- The three state projects and projects in the WAP were "scored"
using monthly models for the species flows and annual pulse flows,
not the higher pulse flows. There was an understanding that these
projects could potentially reduce higher peak flows, but these
criteria would not change as projects went from the reconnaissance
stage in the WAP to feasibility stage. As other water projects
are added to the "possible" portfolio, they will be considered
(scored) on a case-by-case bases regarding impact to pulse flows.
Pulse flows are important and the FWS cannot set an absolute rule
about further reductions when evaluating water related activities
of the Program. Some impact is acceptable, but the impact should
not be significant. A decision on significance must be made on a
case-by-case basis. The WAP implemented during the Program should
have no greater impact on target flows than the WAP as analyzed in
the EIS.
- The process used for evaluating projects in the WAP is not in
the WAP and should be documented and included in future drafts of
the plan.
- There was agreement that many of the WAP project are not
storage, and these typically will not negatively impact pulse
flows.
- The Environmental Account will initially be managed for
species flows and annual pulse flows. The account manager may
manage for average peak flows with experience.
Depletions Plans
- The FWS does not want new depletions plans to aggravate
shortages to average annual peak flows and 2.5 - 5 year peak
flows.
- FWS will investigate further how Nebraska's new depletions
plan could/should operate in regard to pallid sturgeon in the
lower Platte.
Pallid Sturgeon
- FWS does not have enough information to develop any specific
flow or habitat requirements for pallid sturgeon. The Program
will help fill this knowledge gap in collecting monitoring and
research information. More research is needed on the pallid
sturgeon before any target flow or habitat requirements are
determined.
- FWS outlined their position regarding pallid sturgeon in a
letter from Ralph Morgenweck to Mike Besson, then Governance
Committee Chair, dated December 30, 1999.
- The FWS will provide the GC with a "straw dog" proposal for
testing the assumption by their July meeting and to the TC for
their review before July. At the same time, the FWS will also
provide the GC more information regarding any sturgeon flow
requirements that could impact the states' development of water
surpluses to the target flows for the central Platte.
General
- The FWS stated that the Program is to assist in species
recovery, not to recover the species. There is a current effort
to look at species recovery needs and to identify the necessary
contribution of the Platte to that recovery effort. The Platte
cannot be held responsible for actions that impact the species
outside of the region.
- The necessary NEPA/ESA analysis for individual land and water
actions during the Program will be determined on a case-by-case
basis. Some may require a CE, others an EA, and still others an
EIS.
- The FWS noted that the intent of the Program should be to
develop species habitat in accordance with the Cooperative
Agreement, and not to compare different habitat types. Monitoring
and research should provide a comparison of the importance of
different habitats, in addition to determining the biological
response of target species to Program activities.
Decisions
- Agreement that the Program goals and
objectives as written in the Proposed Platte
River Recovery Implementation Program are
still valid.
For further information about the Partnership,
contact any Governance Committee member.
For comments and questions about this website,
please email
Buck Feist or call 406-247-7607
